HPCx Monthly Report, August 2009 |
||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||
Information on the utilisation, disk allocations, slowdowns and helpdesk statistics can be found in the associated SAFE monthly report.
Dates covered: 08:00 1 August to 08:00 1 September 2009
Number of hours: 744
Incidents
The following incidents were recorded:
| Severity | Number |
| 1 | 0 |
| 2 | 0 |
| 3 | 10 |
| 4 | 0 |
Details of severity level 1 incidents
None this month.| Attribution | SEV-1 Incidents | MTBF |
| IBM | 0 | ∞ |
| Site | 0 | ∞ |
| External | 0 | ∞ |
| Overall | 0 | ∞ |
| Attribution | UDT | Serviceability |
| IBM | 0:00 | 100% |
| Site | 0:00 | 100% |
| External | 0:00 | 100% |
| Overall | 0:00 | 100% |
Daresbury Laboratory
| Name | Days |
| Ashworth | 3.9 |
| Porter | 5.7 |
| Sunderland | 6.0 |
| Plummer | 5.0 |
| Jones | 1.9 |
| Todorov | 6.0 |
| Total Days | 28.5 |
| Total FTEs | 1.6 |
EPCC
| Name | Days |
| Simpson | 4.7 |
| Henty | 6.7 |
| Gray | 10.0 |
| Weiland | 0.8 |
| Sim | 5.0 |
| Beckett | 13.6 |
| Trew | 4.0 |
| Johnson | 2.1 |
| Bethune | 6.0 |
| Other | 1.5 |
| Total Days | 55.9 |
| Total FTEs | 3.1 |
Daresbury Laboratory
| Name | Days |
| Andrews | 3.3 |
| BITD | 20.0 |
| Franks | 3.6 |
| Morey | 6.0 |
| Kalavsky | 20.9 |
| Jones | 1.2 |
| Stone | 2.4 |
| Total Days | 57.4 |
| Total FTEs | 3.2 |
EPCC
| Name | Days |
| Brown | 21.0 |
| Nazarova | 7.5 |
| Total Days | 28.5 |
| Total FTEs | 1.6 |
| Metric | TSL | FSL | Monthly measurement |
| Technology serviceability | 80% | 99.2% | 100% |
| Technology MTBF (hours) | 200 | 300 | ∞ |
| Number of AV FTEs (See Note 1) | 3.25 | 5.25 | 4.7 |
| Non In-depth queries resolved within 3 days | 85% | 97% | 100% |
| Number of AM FTEs | 2.75 | 4.75 | 4.8 |
| A&M Serviceability | 80% | 99% | 100% |
Note 1: The Contractual AV target for August '09 is 4.0 FTEs.